Victoria General Hospital, Victoria BC

May - 2009

MR 06-01

Project Details
District- Public
Project Schedule
Completed 7 months
Design: Nov 5
Construction Feb 06
First Patient: May 06

Description:

  • 1.5 Tesla Magnet
  • Complete 1600 sq-ft interior Medical Imaging Department renovation
  • Complete Electrical and Mechanical systems upgrade
  • Construction was completed without affecting the day to day operations of the 2nd MRi system located within the construction site or compromising patient safety
  • Project was completed in 4 phases