Surrey Memorial Hospital, Surrey BC

Sep - 2010

VCT | 08-85

Project Details
District - Public          
Project Schedule
Completed 8 weeks
Design: Feb 8-23
Construction Mar 7 -15
VCT delivery &.Apps: Mar 17-31
First Patient April 1., 2008

Description:

  • Installation of one (1) Lightspeed VCT
  • Interior room finishes upgrade.
  • Upgrade power feeder system to accommodate the new equipment