Stevenson Memorial Hosptial - Alliston, ON

Jul - 2009

VCT ABS | 07-64

Project Details
District: Public
Project Schedule
Completed : 6 months
Design: Nov 08
Construction: Feb 09
First Patient: June 09

Virtual Walkthrough

Description:

  • New 1700 sq-ft ABS VCT department with Skylight feature
  • Brick & Stucco Exterior facade
  • Six (6) month time frame from design to first patient.
  • Turnkey Project included a complete design partnership with the client.
  • ABS comes complete with tie-ins to the existing hospital and
  • apable of relocation / renovation / expansion.
  • Noncombustible hospital grade construction.

 

Nature of Geneer's Involvement

  • Due to the time-line and type of structure required, a modular building was constructed off-site, while site preparations took place for the addition to the hospital.
  • Site was made ready and modules were delivered and assembled on-site.
  • An integral link was created to tie the new building to the existing hospital including all services (ex. Med-gas, plumbing, nurse call and code-blude etc...)
  • Incorporated into the design of the addition was a poprietary HVAC system.
  • The new building consisted of the CT suite and control room, patient prep area, administration offices, radiologists, reading room, equipment/mechanical room, washroom and a patient waiting area.