St. Boniface General Hospital, Winnipeg, MB

Nov - 2007

VCT 2000 | 07-50

Project Details
District: Public
Project Schedule
Completed : 4 months
Design: July 2007
Phase 1 Construction: Aug 16 - Sept 6
VCT Delivery & Apps: Sept 7 - 28
Phase 2 Construction: Sept 28 - Oct 19
VCT Delivery & Apps: Oct 19 - Nov 2
First Patient: November 3, 2007

Description:

  • Two (2) Phase Construction Schedule.
  • Two (2) VCT 2000 Computed Tomography Scanner.
  • Complete Electrical & Mechanical systems upgrade.
  • Two (2) C.T. Suites renovations & Scanner replacements.
  • Upgrade Interior finishes.
  • Accelerated schedules for minimum down time.