Seaman Family MRI -Foothills. Calgary AB

Mar - 2011

Renovations to accomodate new 3T MRI System| 10-227

District: Public
Completed : 10 Weeks, March 2011

Description:

  • Build Staging to second floor level including a lifting gantry and staging platform to open the building envelope allowing the removal of the existing 3T magnet.

 

  • Construction Project Management

 

  • Complete Department renovation, including MRI suite, equipment room, and control room.

 

  • Upgrades to electrical, mechanical, millwork, structural concrete slab, floor finishes and room finishes.

 

  • Coordinating the removal of existing 3T MRI system and placement of the new 3T magnet and MRI system components

 

  • Close up of the building envelope and make good exterior finishes/landscape.