QE II MRI, Grand Prairie AB

Mar - 2011

MRI | 10-251

District: Public
Completed : 4 Months, March 2011 

Description:

  • Complete Department retrofit to accomodate new Wide Bore MRI system site. Preparation included infrastructure services to place a mobile MRI at the hospital.

 

Nature of Geneers' Involvement

  • Develop the scope of work that outlined the construction related requirements to upgrade an existing MRI suite to accept a new G.E. Healthcare MRI system, including modifications to the MRI suite, equipment room, control room and patient prep area.

 

  • Construction project management services.

 

  • Select, engage and direct consulting team.

 

  • Architectural & R.F. sheild modifications.

 

  • Electrical upgrades.

 

  • Mechanical upgrades including supply & installation of a new 15 ton proprietary chiller.

 

  • Exterior courtyard modifications.

 

  • Temporary power for mobile MRI unit.

 

  • Link tunnel between Hospital & mobile MRI - including lighting and heating.