Lethbridge Regional Hospital Lethbridge, Alberta

Aug - 2006

Infinia II | 06-07

Project Details
District: Public
Project Schedule
Completed : 4 months
PHASE 1
Design: April 12
Construction: May 3-17
First Patient: June 2006
PHASE 2 & 3
Design: June 12
Construction: July 23
First Patient: Aug 30

Description:

  • Included installation of two (2) Infi nia II w/ Hawkeye systems
  • Complete Electrical and Mechanical systems upgrade
  • Interior room renovation complete with room fi nish upgrades
  • Included installation of one (1) Millenium MPR
  • Project completed in three (3) phases