False Creek Surgical Centre, Vancouver BC

Sep - 2010

3.0T MRi/Definium 8000 | 06-17

Project Details
District - Private
Project Schedule
Completed 8 weeks
Design: Oct 23-Nov 10
Construction: Nov 13-Dec 12
First Patient: Dec 15, 2006

Description:

  • 2 phase project
  • Definium 8000 X-Ray system
  • Complete 3.0 T room renovation including RF shielding system
  • Electrical & Mechanical system upgrades including New power distribution
  • High end interior finishes with custom made modular millwork in MRi room.
  • Complete D8000 room renovation including overhead “Unistrut” support system for equipment bridge