Brandon Regional Hospital Brandon, Manitoba

Dec - 2006

CT LS VCT | 06-16

Project Details
District: Public
Project Schedule
Completed : 3 months
Design: Oct 9 - Dec 8
Phase 1: Nov 6 - 10
Phase 2: Nov 11 - Dec 8
Phase 3: Nov 11 - Dec 14
Equipment Install & Apps: Dec 6 - 15
First Patient: Dec 16

Description:

  • CT Lightspeed VCT.
  • Complete 1600 sq-ft interior Medical Imaging Department renovation.
  • Complete Electrical and Mechanical systems upgrade.
  • Project completed in three (3) phases to allow the existing
    department to operate.